3. Diagnosis

3.2.1 Starting the test routine

3.2.2 Concluding the test routine

3-8
1. Switch off the operating voltage supply (pins 1 and 2) on
the node.
2. Switch off the operating voltage supply on the output
modules..
3. Remove the cover over the DIL switches.
4. Note the setting of the address selector switch and of the
DIL switches.
5. Set field bus address 99.
Set DIL switch element 1 to ON.
6. Switch on the operating voltage supply (pins 1 and 2).
7. Start the test routine:
set DIL switch element 1 to OFF.
If faults occur when the test routine is started, the red LED on
the node will flash fast.
The procedure must then be repeated.
1. Switch off the operating voltage supplies (pins 1 and 2)
on the node.
2. Reset the address selector switch and the DIL switch el-
ements to their original positions again.
Switch on the operating voltage supply again when the test
routine is concluded:
S
on the node
S
on the output modules