Rotax 125 MAX DD2 evo Installation Instructions And Operators Manual page 33

Hide thumbs Also See for 125 MAX DD2 evo:
Table of Contents

Advertisement

Figure 4.11
1
Solenoid valve
Connectors (signed
3
green)
Step
Procedure
5
Remove isolation tape from the shift
contact wire (pos. 1) and loosely fas-
ten with a tie wrap (pos. 2) (about 130
mm from the cable lug).
Figure 4.12
1
Contact wire
NOTE
Do not tighten tie wrap yet in order to be able to
change its position later on.
3
Page 8
Edition: September 01 2019
BRP-Rotax
INSTALLATION MANUAL
Ignition coil
2
4
Cable tie
2
Tie wrap
Step
Procedure
6
Fasten the cable lug (pos. 3) to the
shift contact assy. using the Plastite
screw M6x25 (pos. 4). Pay attention to
correct sequence of the components!
See following Figures.
For correct adjusting of the plastite
screw find the according section inside
the latest Operators Manual.
NOTE
Fasten the cable lug (pos. 3) between the fuel
tube 8 mm (pos. 2) and the Plastite screw
M6x25 (pos. 4). See following Figure.
Figure 4.13
Shift contact assy.
1
Cable lug
3
NOTE
The correct adjustment of the shift contact is de-
scribed in the Operators Manual, section "Ad-
justment of gear shifting".
Procedure
Step
7
Fasten the wire of the shift contact
assy. with a tie wrap (pos. 1) on the
bottom of the engine.
2
Fuel tube
4
Plastite screw M6x25
Effectivity: 125 MAX DD2 evo

Advertisement

Table of Contents
loading

Table of Contents