This chapter describes initial commissioning of the fire control panel FC361-xx.
Install devices
Before inserting or connecting a device, stick the ID number onto the layout plan.
The adhesive strip with the ID number can be found on the bottom of the device.
w The detector line is not connected to the control panel.
w The power supply is disconnected from all devices with external power supply.
1. Install and wire the devices and stick the ID number for each device onto the
layout plan.
2. Mount the detector dust caps on the optical point detector if necessary.
3. Install the designation plate if necessary.
Check the detector line
NOTICE
Simultaneous connection of line tester and detector line to the control panel
Damage to line tester or control panel
Do not connect the line tester and the detector line to the control panel at the
same time.
w The detector line is not connected to the control panel.
1. Connect the Line Tester FDUL221 to the newly installed detector line.
2. Test the detector line for short-circuits, open lines and earth faults.
3. Check the number of the devices on the detector line using the display on the
line tester.
4. Check the branch-off position of the stubs and the number of devices at the
stubs.
5. Check the type of all devices.
6. Remedy any errors and carry out the acceptance test again.
Detailed information about the Line Tester FDUL221 is available in document
008250. See chapter 'Applicable documents [➙ 9]'.
A6V10421795_en--_g
2016-11-18

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fc361-zzFc361-zaFc361-yzFc361-ya

Table of Contents