System Commissioning; Acceptance Of The System - Siemens Second Wind Function Manual

Fail-safe operation of the mobile panel 277f iwlan
Table of Contents

Advertisement

System commissioning

5.1

Acceptance of the system

Introduction
All of the relevant application-specific standards and the procedure described in this chapter
must be observed in the course of final acceptance of the plant.
Important information about the final acceptance of a plant with fail-safe systems
Note
This document only provides detailed information about the additional acceptance
procedures required for operation of the Mobile Panel 277F IWLAN HMI device.
In the course of final inspection of the plant, you must strictly observe the detailed
description of basic measures to be taken provided in the "S7 Distributed Safety, Configuring
and Programming" manual, chapter "Final inspection of the plant."
Requirement
● The hardware configuration was created in HW Config.
● The safety program was created and generated.
● A backup of the STEP 7 project was created.
Basic procedure
The acceptance of the plant includes the following areas:
● Configuring the F CPU and fail-safe I/O
● Safety program
● Effective ranges and transponders
Acceptance of the configuration for the F CPU and fail-safe I/O
● Print and archive the hardware configuration data.
● Check the following parameters in the hardware configuration data:
● Backup the hardware configuration data along with your STEP 7 project.
A detailed description is provided in the "S7 Distributed Safety, Configuring and
Programming" Manual, chapter "Acceptance of the configuration for the F-CPU and fail-safe
I/O."
Fail-safe operation of the Mobile Panel 277F IWLAN
Function Manual, 08/2008, 6AV6691-1FQ01-2AB0
– Parameters of the F-CPU
– Safety-relevant parameters of the fail-safe I/O:
Unique PROFIsafe addresses, additional PROFIsafe parameters
5
77