10 Commissioning

10.1 Installing and checking a detector line

A6V10421795_en--_k
This chapter describes initial commissioning of FC360 fire control panel.
To install devices
Before installing or connecting a device, stick the ID number onto the layout plan.
The adhesive strip with the ID number can be found at the bottom of the device.
 The ↑ detector line is not connected to the fire control panel.
 The power supply is disconnected from all devices with external power supply.
1. Install and wire the devices and stick the ID number for each device onto the
layout plan.
2. Mount the detector dust caps on the optical point detector if necessary.
3. Install the designation plate if necessary.
To check the detector line
NOTICE
Simultaneous connection of line tester and detector line to the panel
Damage to line tester or panel
Do not connect the line tester and the detector line to the panel at the same
time.
 The detector line is not connected to the panel.
1. Connect the Line Tester FDUL221 to the newly installed detector line.
2. Test the detector line for short-circuits, open lines and earth faults.
3. Check the number of the devices on the detector line using the display on the
line tester.
4. Check the branch-off position of the stubs and the number of devices at the
stubs.
5. Check the type of all devices.
6. Remedy all errors and carry out the acceptance test again.
Detailed information about the Line Tester FDUL221 is available in document
008250. See chapter 'Applicable documents [➙ 9]'.
Commissioning
Installing and checking a detector line
10
109 | 151

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fc362 seriesFc361-zzFc361-zaFc362-zzFc362-za

Table of Contents