Commissioning

Planning
l
Assign the field devices to the floor plan as per local regulations.
l
Document the panel parameters (see Appendix A).
l
Calculate battery standby time (see chapter 11).
Field installation
l
Install detection lines (detectors and manual call points) and terminate with EOL
element.
l
Install control (sounder) lines and terminate with EOL element.
Warning
Pay attention to external voltage (AC 230 V)!
Panel installation
l
Fire control panel must be mounted.
l
Connect all detection lines or terminate with EOL element.
l
Connect all control lines or terminate with EOL element.
l
Connect alarm and fault dialer.
l
Inscription stripes must be inserted for zone ind. field (optional).
l
Switch off the main supply fuse AC 230 V.
l
Connect the power cable and check the earth connection.
l
Switch on the main supply fuse AC 230 V.
l
Place and connect battery.
l
Fill in and place the provided label at the top, right-hand side of the housing.
Programming
l
Initial start-up of the panel.
l
Program the system and resolve the faults.
Function test
l
Initiate lamp test and check all LED, internal buzzer.
l
Test each device (Detector, MCP, etc.) individually and check the correctness of
the system behavior in terms of outputs (e.g. Sounder, Fire output, etc.).
l
Test fire and fault transmission.
l
Make sure that the panel is in normal operation, the buzzer and all system parts are
enabled.
The system can now be handed over to the customer.