Checking the Air Supply
After the tubing is installed, use the following procedure to connect the air supply.
1. Supply clean, dry compressed air to the filter regulator.
2. Turn on the air supply.
3. Adjust the filter regulator.
4. Supply pressure must be 10 psi greater than the spring range of the actuator but
may not exceed the rated actuator pressure. Refer to the valve or actuator
instruction manual.
5. Inspect the tubing connections between the filter-regulator and the positioner for
leaks.
6. Verify that the tubing is not bent or crushed.
7. Verify that all fittings are leak tight.
NOTE
For detailed information on pneumatic connections refer to "Pneumatic Connections" on
page 35.
© 2018 Baker Hughes, a GE company, LLC. All rights reserved.
Do not use Teflon pipe seal tape. The Teflon tape can shred into
particles that are harmful to the pneumatic components.