2. Commissioning
2.3

Commissioning the CPX terminal on the Interbus

2-38
In order to avoid faults (e.g. configuration and parameterisa-
tion faults) during commissioning:
Please observe the general commissioning instructions in
the CPX system manual.
Check the DIL switch settings before using and replacing
CPX terminals.
Note the instructions for switching on the power supply in
section 2.1.5.
Check the configured address range (process data and
assigned input and output bytes). If necessary, test the
I/Os.
Check the address assignment of the I/Os on the
CPX terminal. In order to do this, you can, if necessary,
force the I/Os (see CPX system manual).
Make sure that the desired parameterisation of the
CPX terminal in the initialization phase or after fieldbus
interruptions is carried out by the module. This is to en-
sure that if the CPX terminal is replaced, the new terminal
will also be operated with the desired parameter settings.
Carry out spot checks if necessary to check parameterisa-
tion with the handheld.