Installation
4 4 . . 4 4 . . 1 1 I I n n s s t t a a l l l l i i n n g g B B a a t t t t e e r r y y D D e e t t e e c c t t I I n n t t e e r r f f a a c c e e C C o o n n n n e e c c t t i i o o n n s s
NOTE 1
NOTE 2
To install wiring:
1.
If wiring the IBC battery detect interface terminals using line-up-and-match wiring using the inter-cabinet
wiring access pass-through (see
terminals using the top entry access, proceed to
using the bottom entry access, proceed to
NOTE
2.
Line-Up-and-Match Wiring. Route the battery detect interface wiring from the UPS battery detect
interface terminals through the top inter-cabinet access pass-through (see
and IBC to the IBC battery interface terminal block TB2. See
paragraph
requirements. Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in
paragraph
3.
Proceed to
4.
Top Entry Wiring. Remove the top conduit plate (see
conduit requirements and mark their location. Drill and punch all conduit holes in the top conduit plate prior
to mounting on the IBC. Install the conduit plate and install all conduit runs into the plate. Pull the wiring
through the conduit into the wiring area.
NOTE
5.
Route the battery detect interface wiring from the UPS battery detect interface terminals through top of
the IBC to the IBC battery interface terminal block TB2. See
3.2.3 IBC Interface Wiring
Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in paragraph
1.7 For More
6.
Proceed to
7.
Bottom Entry Wiring. Remove the bottom conduit plate (see
IBC. Identify all conduit requirements and mark their location. Drill and punch all conduit holes in the
bottom conduit plate prior to mounting on the IBC. Install the conduit plate and install all conduit runs into
the plate. Pull the wiring through the conduit into the wiring areas.
NOTE
.
8.
Route the battery detect interface wiring from the UPS battery detect interface terminals through the
bottom of the IBC to the wiring channel on the left side of the IBC (see
the wiring channel to the IBC battery interface terminal block TB2. See
See paragraph
36
Eaton 93PM Integrated Battery Cabinet-Small (IBC-S) Installation Manual 164000305—Rev 06
Disconnect terminal block plug from terminal block to wire plug.
If the inter-cabinet wiring access pass-through is not used to install the battery detect
interface wiring connections, conduit must be installed between the battery cabinet and
the UPS cabinet.
Figure
In multiple IBC installations, route the battery interface wiring between IBCs through the
top of the adjacent IBC using the top side inter-cabinet access pass-through (see
Figure
10).
3.2.3 IBC Interface Wiring
Preparation,
1.7 For More
Information, for UPS cabinet terminal locations.
Step
10.
In multiple IBC installations, route the battery interface wiring between IBCs through the
top of the adjacent IBC using the top inter-cabinet access pass-through (see
Preparation,
Information, for UPS cabinet terminal locations.
Step
10.
In multiple IBC installations, route the battery interface wiring between IBCs through the
top of the adjacent IBC using the top inter-cabinet access pass-through (see
3.2.3 IBC Interface Wiring
10) proceed to
Step
2; if wiring the IBC battery detect interface
Step
5; if wiring the IBC battery detect interface terminals
Step
8.
Figure 18
Table
7, and
Figure 19
Figure
17) from the top of the IBC. Identify all
Figure 18
Table
7, and
Figure 19
for wiring and termination requirements.
Figure
Preparation,
Table
7, and
Figure
10) of the UPS cabinet
for terminal locations. See
for wiring and termination
Figure
for terminal locations. See paragraph
17) from the inside bottom of the
Figure
Figure
13). Route the wiring along
Figure 18
for terminal locations.
Figure 19
for wiring and termination
10).
10).