4 Connection and commissioning
The gas discharge line must have a minimum inside diameter of 4 mm. A 6 mm
compression fitting connection must be provided.
Note
No additional devices can be connected to the line.
52
Exhaust gas lines must be routed separately.
Danger
An overpressure must not develop in the line.
4.2.1
Note
The connection of the carrier gas according to the aforementioned guide-
lines should take place with the ball valve closed first.
It must be ensured that a pressure of 5.5 bar is provided.
After connection, the supply lines must be flushed by opening the com-
pression fitting connection on the inlet filters.
The power supply to the measuring unit can be re-established after the
ball valve is opened and a wait time of at least 15 min is observed.
Monitoring of the carrier gas pressure now takes place with the internal pressure
transducer and analytical computer. The pressure at the analytical computer can
be read on the "Status" screen and fine adjustments can be made when checking
the display value.
Connection values: 5.5 bar ( 10%)
Manual PGC 9300 EN07 June, 18th 2018