3 Gas chromatograph PGC 9300

3.6 Analysis process

The following four diagrams Figure 10: Flushing (default position), Figure 11: Ap-
plication of pressure, Figure 12: Injection and Figure 13: Analysis show the basic
analysis sequence. The process is only shown for one channel for the purpose of
simplification.
40
- Default position
Carrier gas (green)
is connected to the injector via a solenoid valve with a pres-
sure of 5.5 bar. It applies pressure to the micro valves for the injection and
gas
sample, whereby they are closed (red). The pressure-regulated carrier gas flows
continuously over flow resistors through the analysis and reference column.
- Flushing (Figure 10: Flushing (default position))
The solenoid valve for the gas sample is switched to ventilation, the pressure at
the micro valve is relieved and the valve opens. The gas stream flows through the
sample loop. Continuous flushing that is always activated takes place at the PGC
9300.
Figure 10: Flushing (default position)