OPERATION
It is essential that the lock-ring is seated correctly.
Put the wheel assembly into a safety cage and inflate the tyre
●
to a pressure of 1 - 1.5 Bar.
Visually check the lock-ring is still seated correctly and there
●
is no clearance between it and the loose flange Fig. 3.
If the lock-ring is not in the correct position stop the procedure
●
as the lock-ring may be ejected from the groove resulting in
possible injury.
Deflate the tyre and repeat the procedure.
If the lock-ring is correctly positioned continue to inflate the
tyre to the value given in the previous table.
Before removing the wheel assembly from the safety cage
●
repeat the visual check.
When refitting the wheel assemblies, tighten at least 2 diago-
●
nally opposite wheel nuts and then tighten the tyres to the
specified torque in the order shown in Fig. 4.
Tightening torque: 80 Kg.m
Retighten to the specified torque after 5 hours operation.
●
PW160-7H VEAM390100
WARNING
CHECK AFTER STOPPING ENGINE
YES CORRECT ASSEMBLY
Clearance
NO WRONG ASSEMBLY
193