4 Option Components
Power-Up Diagnostics
An LED test is performed each time the drive is powered up. The initial boot sequence may take several seconds. After
the LEDs have completed the diagnostic LED sequence, the option is successfully initialized. The LEDs then assume
operational conditions as shown in
Sequence
1
2
3
4
5
6
12
Table
4.
Table 5 Power-Up Diagnostic LED Sequence
Module Status (MS)
Green
Red
Green
Green
Green
Green
YASKAWA ELECTRIC SIEP C730600 70B V1000 Option SI-EP3/V Technical Manual
Network Status (NS)
OFF
OFF
OFF
Green
Red
OFF
Time (ms)
250
250
250
250