Hard disk drives (HDD), solid state drives (SSD) and 2.5-inch PCIe-SSD
7.4.1

Preliminary steps

Only applicable for removing intact HDD/SSD modules:
Ê Before removing a non-defective HDD/SSD module, put the drive into
"Offline" mode using your RAID configuration software.
7.4.2

Removing a 2.5-inch HDD/SSD module

Ê Remove the HDD/SSD module to be replaced from the server as described
in section
"Removing a 2.5-inch HDD/SSD module" on page
7.4.3

Installing a 2.5-inch HDD/SSD module

Ê Install the new HDD/SSD module into the empty drive bay as described in
section
"Installing 2.5-inch HDD/SSD modules" on page
7.4.4

Concluding steps

Perform the following procedures:
"Performing a RAID array rebuild" on page 75
Ê
"Updating ServerView RAID Manager" on page 80
Ê
102