Inspect all lifting devices. Slings, chains, and/or
cables used for lifting components must be in-
spected daily for serviceable condition. Refer to
the manufacturer's manual for correct capacities
and safety procedures when lifting components.
Replace any questionable items.
Slings, chains, and/or cables used for lifting com-
ponents must be rated to supply a safety factor of
approximately 2X the weight being lifted.
When in doubt as to the weight of components or
any assembly procedure, contact the Komatsu
area representative for further information.
Lifting eyes and hooks should be fabricated from
the proper materials and rated to lift the load being
placed on them.
Never stand beneath a suspended load. Use of guy
ropes are recommended for guiding and position-
ing a suspended load.
Before raising or lifting the body, be sure there is
adequate clearance between the body and over-
head structures or electric power lines.
Be sure that the lifting device is rated for at least a
45 ton capacity.
1. Attach lifting device to dump body and lower over
the truck frame. Align body pivot and frame pivot
holes.
2. Install shims (9, Figure 3-1) in both body pivots,
as required, to fill the outside gaps and center the
body on the frame pivot. Do not install shims at
the inside.
A minimum of 1 shim is required at the outside end of
both frame pivots.
3. If not already installed, install retainer (1) and
capscrews (2) to hold bushing (12) in place.
Tighten capscrews to 40 ft. lbs. (55 N.m) torque.
B3-2
4. Align the hole in pivot pin (6) with capscrew hole
in pin retainer (part of body pivot ear, 7) and push
the pivot pin through the shims (9), frame pivot
(10), and into the pivot bushings (8, 12) in each
side of the body pivot.
5. Install capscrew (4) through each pin and tighten
the locknuts (5) to 407 N.m (300 ft. lbs.) torque.
Be sure locknuts (5) are in good condition.
6. Align hoist cylinder upper bushings with the hole
through the body. With pin retaining capscrew
hole and the retaining hole in dump body aligned,
install the pin.
7. Install the pin retaining capscrews (4) and locknuts
and tighten to 407 N.m (300 ft. lbs.) torque. Be
sure locknuts are in good condition.
8. Install mud flaps, rock ejectors, electrical cables
and lubrication hoses.
FIGURE 3-3. HOIST CYLINDER MOUNT (UPPER)
1. Dump Body
2. Hoist Cylinder Pin
Dump Body
90444
3. Hoist Cylinder
4. Capscrew & Locknut