Section 10
Establishing connection and verifying the IEC 61850 communication
10.3
108
There are no settings needed for the IEC/UCA 61850-9-2LE communication in the
local HMI branch Station communication. Make sure that the optical fibres are
connected correctly. Communication is enabled whenever the merging unit starts
sending data.

Verifying the communication

To verify that the communication is working a test/analyzing tool, for example ITT600,
can be used.
Verifying redundant IEC 61850-8-1 communication
Ensure that the IED receives IEC 61850-8-1 data on the selected Ethernet ports.
Browse in the local HMI to Main menu/Diagnostics/Communication/Ethernet
status/Access point/APStatusRedundant/RCHLCCH:1 and check that
ChARedStatus and ChBRedStatus are shown as Ok. Remove the optical connection to
one of the Ethernet ports. Verify that either signal status (depending on which
connection that was removed) is shown as Error and the that other signal is shown as
Ok. Be sure to re-connect the removed connection after completed verification.
Generator protection REG670 2.2 ANSI and Injection equipment REX060, REX061, REX062
1MRK 502 073-UUS A
SEMOD172108-24 v10
Commissioning manual