Preparation Overview; Site Preparation Checklist For Ex3200 Switches; Table 31: Site Preparation Checklist; Chapter 6 Preparation Overview - Juniper EX3200 Hardware Manual

Hide thumbs Also See for EX3200:
Table of Contents

Advertisement

CHAPTER 6

Preparation Overview

Site Preparation Checklist for EX3200 Switches

Table 31: Site Preparation Checklist

Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed switch
tolerances.
Power
Measure distance between external power
sources and switch installation site.
Locate sites for connection of system
grounding.
Calculate the power consumption and
requirements.
Hardware Configuration
Copyright © 2016, Juniper Networks, Inc.
Site Preparation Checklist for EX3200 Switches on page 57
Environmental Requirements and Specifications for EX Series Switches on page 58
General Site Guidelines on page 62
Site Electrical Wiring Guidelines on page 63
Rack Requirements on page 64
Cabinet Requirements on page 65
Requirements for Mounting an EX3200 Switch on a Desktop or Wall on page 65
Clearance Requirements for Airflow and Hardware Maintenance for EX3200
Switches on page 66
The checklist in
Table 31 on page 57
preparing a site for EX3200 switch installation.
For More Information
"Environmental Requirements and
Specifications for EX Series Switches"
on page 58
"Power Specifications for EX3200
Switches" on page 69
summarizes the tasks you need to perform when
Performed by
Date
57

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the EX3200 and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents