Removing A Mid-Mounted Switch From A Two-Post Rack - Extreme Networks Summit X150 Series Hardware Installation Manual

Summit x150 series summit x250e series summit x350 series summit x450 series summit x450a series summit x450e series summit x480 series summit x650 series
Hide thumbs Also See for Summit X150 Series:
Table of Contents

Advertisement

To remove a Summit X480 DC PSU:
1 De-energize the DC circuit.
2 Attach an ESD-preventive wrist strap to your bare wrist and connect the metal end to an appropriate
ground point on the rack.
3 Disconnect the DC power cables as follows:
a Pull the cover off the terminal block.
b Loosen the screws that secure the cable terminals to the terminal block.
c Slide the wires out from under the captive washers.
4 Disconnect the ground wire as follows:
a Loosen the screw that secures the ground wire to the terminal block.
b Slide the wire out from under the captive washer.
5 Push the latching tab to the right as you pull outward on the handle to disengage the PSU internal
connectors (see
Figure
Figure 118: Removing a DC PSU
6 Carefully slide the PSU the rest of the way out of the switch.
7 If a replacement PSU will not be installed, install a cover over the unoccupied power supply bay.
NOTE
Unoccupied power supply bays must always be covered to maintain proper system ventilation and EMI levels.
Leave the ESD strap permanently connected to the switch, so that the strap is always available when
you need to handle ESD-sensitive components.

Removing a Mid-Mounted Switch from a Two-Post Rack

Removing a mid-mounted Summit X480 switch from a rack requires two people to maneuver the switch
and disconnect the mounting hardware.
Summit Family Switches Hardware Installation Guide
118).
SH_163
145