Maintenance Procedures for Summit X650 and Summit X480 Series Switches

Installing the Replacement PSU

To install a replacement Summit X650 DC PSU:
1 Verify that the PSU is right side up (see
Figure
174)
2 Carefully slide the PSU all the way into the power supply bay (see
Figure
174). Push the PSU in until
the latch snaps into place.
CAUTION
Do not slam the PSU into the switch.
Figure 174: Installing a Summit X650 DC PSU
SH_107

Connecting the Ground Wire

To connect the ground wire to the Summit X650 DC PSU:
1 Verify that the DC circuit is de-energized.
2 Identify the grounding point on the front panel of the PSU (see
Figure
175).
3 Insert an M3.5 screw (provided) through the ring terminal and into the grounding point on the PSU.
4 Tighten the screw to 12.6 inch-pounds.
5 Connect the other end of the wire to a known reliable earth ground point at your site.