Figure 73
3. Choose one of the two options:
4. Click Ok.

Scheduling a Consistency Check

Follow these steps to set the properties for a consistency check:
1. Click the Physical tab or Logical tab in the main menu screen, and select the controller.
2. Select Go To->Controller->Schedule Consistency Check. The Schedule Consistency
dialog appears, as shown in the following figure.
Page 92
Maintaining and Managing Storage Configurations
DB09-000202-05 37857-02
Rev. F - May 2011
Set Consistency Check Properties
Stop Consistency Check on Error: The RAID controller stops the consistency check
operation if the utility finds an error.
Continue Consistency Check and Fix Errors: The RAID controller continues the
consistency check if the utility finds an error, and then fixes the error.
Copyright © 2011 by LSI Corporation. All rights reserved.