2 Responsibilities of the Purchaser/Customer

To ensure that the installation of an Innova System meets the purchaser or customer
expectations, it is important to determine who will take responsibility for the various items
during the system installation process. To help you in determining these responsibilities,
review the following checklists with the customer and assign responsibilities as appropriate:
Tool and Test Equipment (
Pre–Installation Checklist (
Contract Changes:
Be sure to inform the customer that the cost of any alteration or modification not specified in
the sales contract are liable to the customer.
The following GE-supplied equipment must be installed by the Hospital's Contractors, per
room drawings:
PDB (Electrical Power Distribution Box or Main Disconnect Panel)
LC Gantry & Table baseplate hole drilling (Per supplied template)
LCD Monitor suspension stationary rails
LC Gantry baseplate grout
LC Gantry baseplate
Omega/Tilt table common baseplate (if applicable)
24
Chapter 7, Section 2,
Chapter 7, Section 5,
2 Responsibilities of the Purchaser/Customer
Direction 5314528-2-1EN, Revision 1
Tools and Test Equipment)
Pre-Installation Checklist)