Pre-Installation Checklist - GE Innova 2100-IQ Preinstallation Manual

Cardiovascular imaging system
Hide thumbs Also See for Innova 2100-IQ:
Table of Contents

Advertisement

Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare

5 Pre-Installation Checklist

GEHC Global Order # :
GEHC On-site Representative :
Name of customer reviewed with :
GEHC PMI :
Target Site Prep Completion Date:
The customer is responsible for proper site preparation and site readiness regardless of any GEHC inspections/assessments.
For MR Magnet Delivery: Ensure cryogen vents, power for the cooling system and exhaust fan system are installed and operational (0.7T,
1.5T & 3T) and chilled water supply is available 24x7 that meets system cooling equipment requirements.
Inspection Date:
Item
GEHC Minimum Requirements
#
Equipment installation drawings must
match actual room size and must meet
clearance requirements. Deviations
that meet installation requirements may
1
be red-lined, if red-lining is allowed by
local code. Seismic requirements are
identified on construction drawings.
Delivery route to installation or storage
area meets requirements and has
been discussed and scheduled with the
2
customer. Ensure floor protection is
discussed, requirements identified, and
will be available at time of delivery and
installation.
Rooms that will contain equipment,
including storage areas, are dust free.
Room security to prevent unauthorized
access and theft has been discussed
3
with customer. The customer is aware of
these security issues, implications and
responsibility.
In room HVAC ductwork and units (in
room) must be mechanically installed
and dust free. Installation rooms appear
to meet environmental conditions (see
4
Further Definitions) and observed
issues have been communicated to the
customer. If being stored, storage area
must meet PIM storage criteria.
Ceiling grid is installed, Unistrut is
located per the installation drawings,
5
and permanent lighting is installed and
operational.
Floor is clean and prepared for final floor
covering. Customer has verified floor
leveling meets the equipment installation
drawings and PIM specs and no visible
6
defects are observed. Gantry and table
baseplate are installed prior to delivery
(if applicable)
Chapter 7 Additional Planning Aids
GE Healthcare Site Readiness Checklist
Customer:
MI Supplier:
Lead Installer:
Phone Number:
Helper:
Predict
(Pre-ship)
Storage:
Is item
Is this
Will
ready?
item
item be
ready?
ready?
X
X
X
Direction 5314528-2-1EN, Revision 1
Validate
Verify
(Mech
(Delivery):
Install):
Is item
Is item
ready?
ready?
X
Comments
If "N", please enter in
comments or action plan
213