5.2 IVUS Floor Conduits

A 3 inches and max. 25 m long conduit between Control and Patient Rooms shall be
prepared below the floor for the IVUS Innova interconnection cables.
Locate the position of the IVUS components in the Control Room, according to the
workflow requirement of the operators.
Establish a 76 mm (3") conduit below floor from the IVUS CPU location in the Control
Room, to the foot end area of the Patient Table in the Procedures Room:
Use similar solutions (i.e. protection against cleaning fluids, etc. ) as it is used for
the Mac-Lab conduit
See also guidance on Typical Layout drawing 4-58f sheets E1 and S2, showing
Mac-Lab and P/M Gas location recommendations.
Chapter 6 Electrical Connections
Locate the Procedures Room exit of the conduit close to the centerline of the
Patient Table
Locate it as close to the Patient Table base as possible, considering :
Room for access to the table for service purposes
Limitation from other cables connected to the table
Location of the table plate
Location of Mac-Lab conduit
Location of Physio or Med Gases connections
The IVUS cables are moving cables, they have to allow the Patient Table
motions (Panning, Lifting and Rotating)
Direction 5314528-2-1EN, Revision 1