17.3 Procedure

17.3.1 Connection of the Power Distribution Box

Hospital main power must enter from the Top. Correct phase sequence during
installation is very important. Phase failure relays are provided to monitor voltages
less than 85%, loss of a phase, or incorrect phase sequence. Corrections to
the phase sequence must be corrected only at the line side of the main circuit
breaker CB1.
1. Connect the ON/OFF, Remote control and Emergency Power Off devices.
Illustration 6-27:
2. If the Fluoro UPS option is installed, remove the L1A, L2A and L3A jumpers linking the
Power Distribution Block 1 and the Power Distribution Block 2.
Illustration 6-28:
3. Connect the Power distribution cables.
196
Direction 5314528-2-1EN, Revision 1
17 PIST0021 - US Fluoro UPS and PDB connection

Advertisement

Table of Contents
loading

This manual is also suitable for:

Innova 3100Innova 3100-iqInnova 4100Innova 4100-iq

Table of Contents