Illustration 6-2: AC Interconnect with Fluoro UPS
Contractor responsibility:
NOTE:
1. Electrical contractor is responsible for providing and connecting cables from the PDB
to the UPS (see table below) and configuring the PDB in bypass mode.
2. GEHC is responsible for powering on the system with the UPS in bypass mode.
3. GEDE is responsible for UPS commissioning.
Table 6-1: A and B cables specification
Cable
Recommended (Note (1))
A
5 X 10 mm2
B
5 X 10 mm2
Note: (1) According to local requirement.
Note: (2) According to local requirement and cable type.
150
UPS CE version
3 ph + N + PE
3 ph + N + PE
Direction 5314528-2-1EN, Revision 1
UPS UL version
Recommended (Note
Max
5 X 3 AWG
5 X 6 AWG
5 X 3 AWG
5 X 8 AWG
(2))
3 ph + N + PE
3 ph + N + PE
1 Power Distribution