Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare
20.3 Procedure
20.3.1 Connection of the Power Distribution Box
1. Connect the ON/OFF, Remote control and Emergency Power Off devices.
Illustration 6-39:
2. If the Fluoro UPS option is installed, remove the L1A, L2A and L3A jumpers linking the Power
Distribution Block 1 and the Power Distribution Block 2.
Illustration 6-40:
3. Connect the Power distribution cables.
230
Hospital main power must enter from the Top. Correct phase sequence during
installation is very important. Phase failure relays are provided to monitor voltages
less than 85%, loss of a phase, or incorrect phase sequence. Corrections to the
phase sequence must be corrected only at the line side of the main circuit breaker
CB1.
Direction 5160944-13-1EN, Revision 2
20 PIST0021 - US Fluoro UPS and PDB connection