Procedure 4
Diagnostic Test Program Execution Check
Execute the following tests from the Diagnostic Test Menu. Refer to chapter 3, Tests and
Diagnostics, for more information on how to perform these tests.
1.
System test
2.
Memory test
3.
Printer test
4.
ASYNC test
5.
Real Timer test
6.
NDP test
7.
PCMCIA test
If an error is detected during any of these tests, go to Procedure 5.
Procedure 5
Replacement Check
The system board may be damaged. Disassemble the 610CT following the steps described in
chapter 4, Replacement Procedures, and perform the following check:
Check
Replace the system board with a new one. If the problem still exists, other FRUs
may be damaged.