Commissioning And Validation; Initial Commissioning - Bosch Rexroth IndraControl S20 Manual

Hide thumbs Also See for Rexroth IndraControl S20:
Table of Contents

Advertisement

DOK-CONTRL-S20*SSDO*8*-AP02-EN-P
IndraControl S20 Module With Safe Digital Outputs S20-SSDO-8/3
8

Commissioning and validation

8.1

Initial commissioning

Step
Set the address.
Install the module in the IndraControl S20 station.
Connect the lines for the bus system and the supply voltag‐
es to the IndraControl S20 station.
Wire the outputs according to your application.
Before applying the operating voltage:
Ensure that there are no wiring errors (e.g. cross-fault
or short circuit) or grounding errors using a multimeter.
Ensure that the functional earthing is connected.
Connect the required voltages to the IndraControl S20 mod‐
ule.
Connect the required voltages (U
After applying the operating voltage:
If possible, measure the ripple of the voltages to en‐
sure that there are no deviations.
Measure the input voltages at the module to ensure
that they are within the valid range.
Check whether the module starts without errors using
the LEDs on the module.
Check the mounting and installation.
Make the required parameterizations.
Program the safety function.
Perform a function test and the validation. Check whether
the safety function responds as planned during programming
and parameterization.
Check whether the module started correctly and whether er‐
rors are displayed when adding the supply voltages using
the diagnostic and status displays.
) to the module.
O
Tab. 8-1:
Commissioning steps
Commissioning and validation
Relevant chapters and literature
Refer to
chapter 5.1.3 "Setting DIP switch" on page
Application description of the IndraControl S20 system
(R911335988)
Application description of the IndraControl S20 system
R911335988
or the documentation of the bus coupler
(R911342782).
Refer to
chapter 7 "Connection examples of the safe out‐
puts" on page
33.
Application description of the IndraControl S20 system
R911335988
or the documentation of the bus coupler.
Refer to
tab. 11-8 "Supply voltage U
58.
For the checklist, refer to
chapter 14 "Checklists" on page
69.
For the module parameterization, refer to
eterizing the module" on page
User manuals of the function blocks used.
For the checklist, refer to
chapter 14.5 "Validation" on page
74.
For the procedure when an error is pending, refer to
9 "Errors: Reporting and troubleshooting" on page
Bosch Rexroth AG
41/85
23.
(actuators)" on page
O
chapter 6 "Param‐
29.
chapter
43.