Requirements for Commissioning
Table 7-7
Step
1
ET 200iS is installed
2
PROFIBUS address is set on the ET 200iS
3
ET 200iS is wired up
4
Zone 1 and Zone 2: Additional check of the
installation and wiring of the ET 200iS,
connections, enclosure, and supply lines.
5
ET 200iS is configured and the parameters are
set
6
The power supply for the DP master is on
7
The DP master has been set to RUN mode
Commissioning the ET 200iS
Table 7-8
Step
1
Turn on the power supply for the ET 200iS.
2
Observe the STATUS LEDs on the ET 200iS
and on the DP master.
ET 200iS Distributed I/O Station
A5E00087831-02
Requirements for Commissioning
Prior Activity
Commissioning the ET 200iS
Procedure
Commissioning and Diagnostics
See...
Section Installation
Section Wiring
Section Wiring
Section Commissioning and
Diagnostics
DP Master Manual
DP Master Manual
See...
Section Wiring
•
Section Commissioning and
Wiring
•
DP Master Manual
7-11