Commissioning And Startup Of The Et 200R; Table 5-2 Software Pre-Requisites For Commissioning The Et 200R; Table 5-3 Hardware Pre-Requisites For Commissioning The Et 200R - Siemens SIMATIC ET 200R Manual

Distributed i/o device
Table of Contents

Advertisement

Commissioning and Diagnosis
5.2
Commissioning and start up of the ET 200R
Software prerequisites for commissioning
Table 5-2
Configuration Software Used
PROFIBUS-DP master configuration tool
(e.g., COM PROFIBUS starting with version
2.1 or STEP 7)
GSD file
A device master file (GSD file in accordance with EN 50170, volume 2) contains all
slave-specific characteristics.
You can download the GSD file from the Internet.
You will find all GSD files under "Downloads" on the Internet page of SIMATIC Cus-
tomer Support
Hardware prerequisites
Table 5-3
ET 200R mounted
PROFIBUS address on DP slave set
ET 200R wired
ET 200R configured
Power on
5–2
Software pre-requisites for commissioning the ET 200R
http://www.ad.siemens.de/csi/gsd
Hardware pre-requisites for commissioning the ET 200R
Activities which have been completed
Explanation
You will have to link in the GSD file to
COM PROFIBUS.
Chapter 3.1
Chapter 3.2
Chapter 3.3
Online aid/manual on con-
figuration software
Manual on DP master
Distributed I/O Device ET 200R
(4)J31069-D0427-U001-A2-7618
See ...