4.3 Check lists to commission SINAMICS S
Checklist for commissioning chassis power units
The following checklist must be carefully observed. Read the safety instructions in the
manuals before starting any work.
Table 4- 2
Activity
Are the environmental conditions in the permissible range?
Are the components correctly installed in the cabinets?
Is the specified air flow for cooling the devices ensured?
Is an air short-circuit between the air inlet and outlet for the chassis components pre-
vented by the installation arrangements?
Have the ventilation clearances for the components been observed?
Is the memory card correctly inserted in the Control Unit?
Are all necessary components of the configured drive line-up available, installed and
connected?
Do the temperature monitoring circuits fulfill the specifications of protective separa-
tion?
Have the DRIVE-CLiQ topology rules been observed?
Have the line-side and motor-side power cables been dimensioned and routed in
accordance with the environmental and routing conditions?
Have the maximum permitted cable lengths between the frequency converter and the
motor (depending on the type of cables used) been observed?
Is the ground for the motors directly connected to the ground for the Motor Modules
(shortest distance)?
Are the motors connected with shielded power cables?
Are the power cable shields connected as closely as possible to the terminal box
across a wide area?
Have the power cables been properly connected to the component terminals with the
specified torque?
Have all of the remaining screws been tightened to the specified torque?
Has the total power of the DC busbar been dimensioned sufficiently?
Has the busbar/wiring for the DC connection between the infeed and the Motor Mod-
ules been dimensioned sufficiently with regard to the load and installation conditions?
Are the cables between the low-voltage switchgear and the power unit protected with
line fuses? Line protection
Have measures been taken to relieve strain on the cables?
For external auxiliary infeed: Have the cables for the auxiliary infeed been connected
according to the Equipment Manual?
Have the control cables been connected in accordance with the required interface
configuration and the shield applied?
80
Checklist for commissioning (chassis)
must be taken into account.
1)
Commissioning with Startdrive
Commissioning Manual, 11/2017, 6SL3097-4AA10-0BP1
OK

Advertisement

Table of Contents
loading

Table of Contents