Requirements for commissioning

3.1

General prerequisites

General
All components are dimensioned for defined mechanical, climatic and electrical
environmental conditions. No limit value may be exceeded, neither during operation, nor
during transportation.
Limit values
In particular, the following must be observed:
● Power supply conditions
● Pollution burden
● Function-impairing gases
● Ambient environmental conditions
● Storage/transport
● Shock stressing
● Vibration stressing
● Ambient temperature
Prerequirements for components involved
The complete system is connected mechanically and electrically, and has been verified in
the following points:
● When handling the components, all ESD measures are observed.
● All screws are tightened with their prescribed torque.
● All connectors are plugged correctly and locked/screwed.
● All components are grounded and connected to shields.
● The load capacity of the central power supply is taken into account.
IBN CNC: NCK, PLC, drive