Plc Commissioning; Creating A Simatic S7 Project - Siemens SINUMERIK 840D sl Commissioning Manual

Hide thumbs Also See for SINUMERIK 840D sl:
Table of Contents

Advertisement

PLC commissioning

7.1

Creating a SIMATIC S7 project

Introduction
It is necessary to create an S7 project for the basic commissioning of the PLC, the Ethernet
and PROFIBUS communication as well as the input/output data areas of the NCK. To do this
you will have to perform the following operations:
● Create a project
● Insert a SIMATIC station 300
● Insert NCU 7x0 in HW Config
● Configure the properties of the network interfaces
● Insert machine control panel and hand wheel
What do you need to be aware of?
Loading the PLC via network interface X130 is also possible if the IP address of the Ethernet
interface is known.
Loading an archive may always be carried out if the communication HMI-NCK is available.
Note
Loading the PLC (CP840) is essential for the configuration of the data path for
saving/restoring the drive data.
At the present time, the HW config of the CP840 can ONLY be loaded alone via network.
Loading the CP840 via PROFIBUS DP2 is not yet possible in the SW version currently
described.
Reference
The PLC interface signals are described in "Parameter Manual 2"
IBN CNC: NCK, PLC, drive
Commissioning Manual, 07/2007, 6FC5397-2AP10-3BA0
Note
The toolbox must have been installed.