Service and Repair Manual
Platform Components
Operational Control Module LED Status
Description
Green and Red LED's
not flashing
Green LED
flashing rapidly
Red LED
flashing with pauses
Safety Control Module LED Status
Description
Green and Red LED's
not flashing
Green and Red LED's
flashing alternately
8
Activate the calibration toggle switch inside
the ground control box 1 time.
Result: The alarm should sound for 1 second
indicating the second calibration step was
accepted. The green LED on the operational
controller should be blinking fast and the red
LED should be blinking three times indicating
that step 3 of calibration is next.
9
Raise the boom until the distance, when
measured between the centers of the pivot
pins shown, equals 167.25 inches / 424.8 cm
± 0.75 inch / 19 mm.
Crushing hazard. Keep clear of
all moving parts of the boom
while the boom is raising. Do not
attempt to measure between the
pivot pins while the boom is
moving.
36
S-60 • S-65 • S-60 TRAX • S-65 TRAX • S-60 HC • S-60X • S-60XC Part No. 1268492
Definition
System calibrated
System in calibration mode
Indicates next calibration
step (ie; 2, 3, etc.)
Definition
System calibrated
System not calibrated
10 Activate and release the calibration toggle
switch inside the ground control box 1 time.
Result: The alarm should sound for 1 second
indicating the third calibration step was
accepted. The green LED on the operational
controller should be blinking fast and the red
LED should be blinking four times indicating
that step 4 of calibration is next.
11 Fully raise and extend the boom.
12 Activate and release the calibration toggle
switch inside the ground control box 1 time.
Result: The alarm should sound for 1 second
indicating the fourth calibration step was
accepted. The green LED on the operational
controller should be blinking fast and the red
LED should be blinking five times indicating
that step 5 of calibration is next.
13 Fully retract and lower the boom to the stowed
position.
14 Using a suitable lifting device, place an
appropriate test weight equal to 750 lbs /
340.2 kg on to the center of the platform floor.
Note: If your machine is equipped with any platform
accessories or options, they must be removed from
the platform OR the weights of those options or
accessories must be subtracted from the test
weights to accurately calibrate the platform load
sense system.
September 2016