Initial Turn-up and Provisioning

............................................................................................................................................................................................................................................................

Initial turn-up sequence instructions

Visual inspection for subrack installation and cabling
Inspect the following:
Verify rack and subrack location and equipment configuration based on engineering
documentation.
Verify any fiber connections to office DDF/ODF based on office documentation.
Verify inter- and intra-subrack fiber connections as specified in Installation Guide and
engineering documentation.
Verify fiber labeling and routing and inspect for damaged or pinched fibers or fibers
that exceed the minimum bend radius.
Verify all electrical and power cable and ground connections as specified in the
Installation Guide.
Note:
Guide.
............................................................................................................................................................................................................................................................
2 - 2
For additional information see the Alcatel-Lucent 1850 TSS-320 Installation
Initial turn-up sequence instructions
PN 8DG08136CAAA
Issue 1 March 2008