Part III: Network turn-up and
testing
Overview
This section starts the process of integrating the Alcatel-Lucent 1850 Transport Service
Switch 5 (1850 TSS-5) into the customer's network. The section provides the procedures
to connect inter-office fibers and verify DCC communications and path switching.
Contents
This part of the document contains the following chapters:
Connecting adjacent network elements
Installation checklist
Table III-1
Section and Chapter
Chapter 7, "Connecting
adjacent network elements"
............................................................................................................................................................................................................................................................
365-372-403R5.1
Issue 1 November 2008
Part III installation checklist
Procedure
"Fiber installation" (p. 7-2)
"OC-3/STM-1/OC-12/STM-4 optical
transmission test" (p. 7-7)
"Automatic protection switching test" (p. 7-8)
"Manual switching tests" (p. 7-10)
"Final operations" (p. 7-12)
Chapter 7
Completed
Required
Yes
No
Yes
Yes
Yes
Yes
Yes
II I- 1