JLG 15MVL Series Service Maintenance Manual page 101

Hide thumbs Also See for 15MVL Series:
Table of Contents

Advertisement

9. Remove the cylinder/anchor block attach pin - snap
ring from the back of the top of mast section-2.
Snap Ring Installation
1. Back of Mast Section-2
2. Cyl./Chain Anchor Block
10. Remove the cylinder rod pin from the cylinder/chain
anchor block.
Cylinder Rod Pin Installation
1. Cylinder Rod Pin
2. Cylinder Rod
3121231
1
2
3
4
3. Pin and Snap Ring
4. Cylinder Rod
1
2
3
3. Cyl./Chain Anchor Block
– JLG Lift –
SECTION 5 - MAST COMPONENTS
11. At the bottom of mast section-1, remove the cylinder
mount bolts, and mount reinforcement plates.
Lift Cylinder Mount Installation
1. Cylinder/Mount Assembly
2. Mount Shims (Mark Shims) 4. Mounting Screws/Washers (a)
Notes: (a) Apply Loctite #242 to threads at final assembly.
NOTE: If mount shims are installed, mark the mast and the
shim to which side the shims came out of for re-
installation.
12. Slide the lift cylinder and mount assembly out of the
bottom of mast section-1 and -2 and place on a suit-
able work surface.
3. Mast Reinforcement Plate
5-11