Installing the Server in a 2-Post Rack

These topics describe how to install the server into a 2-post equipment rack using
one of several rackmount kits.
Step
Description
1.
Install optional components.
2.
Review cautions.
3.
Stabilize the rack.
4.
Install the server in a 2-post rack.
Related Information
"Installing the Server in a 2-Post Rack" on page 51
"Confirming Server and Site Specifications" on page 9
"Preparing for Installation" on page 19
"Installing the Server in a 4-Post Rack" on page 27
"Connecting Cables" on page 77
"Powering On the Server the First Time" on page 91
Installing the 19-Inch Hardmount Kit
(2-Post Rack)
Use these topics to install the server using an optional 19-inch hardmount rack kit
into a 19-inch wide, 2-post rack.
"19-Inch Hardmount Rack Kit (2-Post Rack)" on page 52
Links
"Optional Components" on page 22
"Rack Cautions" on page 23
"Stabilize the Rack" on page 24
"Installing the 19-Inch Hardmount Kit (2-Post Rack)" on page 51
"Installing the 19-Inch Sliding-Rail Kit (2-Post Rack)" on page 59
"Installing the 23-Inch Hardmount Kit (2-Post Rack)" on page 68