4.8
First-time Startup
This section describes the procedure for starting up the Power+ for the first time, after having
completed the installation process described in the previous chapter.
Ensure that the maintenance bypass switch is set to NORMAL (OFF), and that no
1.
load devices are connected to the UPS.
Turn the ac input and ac bypass switch ON and wait (for about 2 minutes) for the
2.
POWER + to initialize.
When applying power to the POWER + , the system automatically runs the startup
process without a need to press the On/Off button.
The start-up sequence begins. The control panel displays the sequence of screens
3.
illustrated below, while the system performs a series of self-tests. (The precise screen
details may vary.)
During this step, the LEDs are also checked sequentially.
28
Figure 11: Start-up screen 1
Figure 12: Start-up screen 2
Figure 13: Start-up screen 3
Figure 14: Start-up screen 4
POWER + RM 50
Gamatronic Electronic Industries Ltd.
VA, N.Am. Std. – User Guide, Release 1.4
K