Download Print this page

Alamo John Deere 6215 Assembly & Instruction Manual page 37

Advertisement

Frame Rail Installation 2 WD & 4 WD
Pre-Installing Frame Rails:
11.
Raising Frame Stabilizer Kit Up Under
Tractor. Using a Floor Jack slide Stabilizer Kit
under Tractor right behind the front wheels. (See
Figure 17). Note the Floor Jack used here has
had channel built for it that cradles the square
shape, this is also good for supporting the frame
rails during assembly. Using Jack helps to align
Stabilizer to frame rails.
12.
Align Stabilizer Kit. Raise Stabilizer Kit
with the Floor Jack up till it is flush up against the
Stabilizer Gusset Support that should already be
bolted to the frame from earlier installation steps
(See Figure 18). This should be this way on the
RH and LH side.
Stabilizer yet this will be done later. Secure the
Stabilizer kit to the Frame Rails with C-Clamps on
both LH and RH (See Figure 19). You may leave
the Floor Jack or remove it.
13.
Align Frame Rails on Front Mount Pads.
Locate the Front Frame rails on the mount pad so
that there is room for the Bolt heads to clear the
Frame Rail. Here we have wedged a Screwdriver
with a 1/4" shank between the Bolt Head and the
Frame Rail. Anything about that size can be used
to keep enough distance so bolt can be removed
and reinstalled without interference. Use a C-
Clamp to hold it in place when aligned. Do this on
Both the RH and LH side. (See Figure. 20)
Stabilizer up
against Gusset
C-Clamps
Figure 19
Machete (JD-62, 63, 6420 Asy Man) 10/04
© 2004 Alamo Group Inc.
(continued)
DO NOT Weld Gusset to
Section 4 - 11
Figure 17
Stabilizer Gusset
Machete
Frame Rail
Figure 18
C-Clamp
Frame Rail
(Front)
Front Rail
Mounting Pad
Figure 20
Stabilizer Kit
1/4"
Shanked
Screwdriver

Advertisement

loading

This manual is also suitable for:

John deere 6415John deere 6320John deere 6420Machete