Frame Rail Installation 2 WD & 4 WD
Pre-Installing Frame Rails:
4.
Front Rail Mounting Pad. There are
two of these Pads; one is used on the left and
one on the right. These Pads are the same
so it will not matter which goes on which side.
(See Figure 9). Set the Pad down over the
Front rail Support aligning the four holes in
pad with the four holes Support. Insert the
four Bolts into the mount pad and plates on
front support mount (See Figure 10). Install
a nut on one or two of the Bolts but do not
tighten them, the Bolts are only installed to
prevent the Pad from moving side to side.
5.
Locate RH and LH Frame Rail. There
are two different frame rails, RH and LH. Start
with either one you want, for illustration we
started with the RH (See Figure 11). Re-
member the LH is the one with the Counter
Weight Mount Tubes welded onto it, (See
Figure 1)
6.
Prepare Tractor Axle Housing. First
look up under Tractor at the rear axle where
the frame Rails mount you will see holes in
the Axle castings on both LH and RH side that
has plastic plugs in them. The Plastic Plugs
will have to be removed now as they cannot
be removed once the Frame Rails are in
place (See Figure 12).
Figure 11
Machete (JD-62, 63, 6420 Asy Man) 10/04
© 2004 Alamo Group Inc.
(continued)
Front Rail
Mounting Pad
P N. 02725900
Figure 9
Front Frame Rail
Support Mount
Figure 10
Figure 12
Section 4 - 9
Front Frame Rail
Mount Pad