Install the Director in a Rack
The following sections provide instructions for installing the Director 2/64 in
either the 9000/10000/11000 rack or in the HP system/e and industry-standard
19-in racks. If you plan to install the director in the optional M-Series Rack, refer
to the HP StorageWorks M-Series Rack Mount Kit Installation Instructions.
Required Tools
Obtain the following tools:
Tips for Installing More than One Switch
Review the following tips:
Transfer the Director to the Lift Device
Use these steps to position the Director 2/64 next to the rack.
Director 2/64 Installation Guide
For a HP system/e and industry-standard 19-in rack:
— #2 Phillips screwdriver
— Torque screwdriver
For a 9000/10000/11000 rack:
— #2 Phillips screwdriver
— Torx head driver T25
Install the first director in the lowest position of the rack, allocated for
switches.
If installing more than one switch, Hewlett-Packard recommends installing an
optional PDU in the bottom of the rack. Hewlett-Packard ships two PDU
power cords with the Director 2/64.
Install additional switches in position directly above one another.
Make sure to connect power cables as you install each individual switch.