Sliding Shelf Installation-For An Hafm Server Only - HP Surestore 64 - Director Switch Installation Manual

Fw 05.01.00 and sw 07.01.00 director 2/64 installation guide (aa-rsngc-te/958-000289-001, june 2003)
Hide thumbs Also See for Surestore 64 - Director Switch:
Table of Contents

Advertisement

3. Connect the other ends of the PDU power cords to separate PDUs (if
Note:
Hewlett-Packard ships two PDU power cords with the Director 2/64.
Figure 25: AC power connections
4. Connect the equipment rack power cords to separate (for redundancy) facility
Sliding Shelf Installation—For an HAFM Server only
This section only applies to a Management Station. Use the following procedure
to install sliding shelf brackets, as shown in
1. Select a U slot above the switch. (It is recommended to select the U slot
2. On each rack rear column, locate the hole (1) that is 2 holes up from the EIA
3. Line up this hole with the threaded hole on the sliding shelf bracket's side.
4. Using a screw (2), attach bracket (5) to the rack.
5. Attach another screw (4) loosely in the hole on the inside face of the
Director 2/64 Installation Guide
installed), as shown in
power cords.
Hewlett-Packard recommends installing an optional PDU in the rack.
WARNING:
Hewlett-Packard power cords are provided for each director
power supply. To prevent personal injury by electric shock, use only the
supplied power cords. Also, verify that the facility power receptacle is the
correct type, supplies the required voltage, and is properly grounded.
power sources, providing single-phase, 120 to 240 VAC current.
immediately above the switch. However, other U slots above the switch may
also be used.)
number of the selected U slot (3).
mounting bracket (5).
Installing and Configuring the Director 2/64
Figure
25; otherwise, connect the two standard AC
Figure
26: