Chapter 1
Migrating to a Cisco CRS-3 Carrier Routing System

Powering up the Replaced Fabric Card

This section describes how to enable power back to the Fabric node, and verify that node is moved to
Powered state.
Prerequisites
Software Requirements
Hardware Requirements
Restrictions
None.
SUMMARY STEPS
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
OL-13669-03
Cisco IOS XR Software Release 4.0.0.T or later release (Cisco IOS XR Software Release 4.0.2 for
multishelf nodes)
ROMMON 1.54 or later version
The LCC to be added must be prepared as described in the
Cisco CRS-3 Carrier Routing System" section on page
The control network must be operational and connected to all chassis.
The power should be off for the FCC to be added.
admin
configure
no hw-module power disable loc 0/SM0/SP
commit
Apply power to the new LCC (Rack 1).
Connect all fabric cables that connect the fabric planes in the new LCC to the FCCs.
Specify that the LED in question is the one on the FCC OIM-LED module.
do show controllers fabric rack-status all detail
do show controllers fabric fabric-backpressure summary
no controllers fabric rack 1 install-mode
commit
do show controllers rack-status all detail
Cisco CRS-1 Carrier Routing System to Cisco CRS-3 Carrier Routing System Migration Guide
How to Migrate to a Cisco CRS-3 Carrier Routing System (16-Slot)
"Prerequisites for Upgrading to a
1-2.
1-37

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the CRS-1 - Carrier Routing System Router and is the answer not in the manual?

This manual is also suitable for:

Crs-3

Table of Contents