Huawei LUNA2000-200KWH-100KW-2H1 Quick Manual

Huawei LUNA2000-200KWH-100KW-2H1 Quick Manual

With smartlogger based microgrid control
Hide thumbs Also See for LUNA2000-200KWH-100KW-2H1:

Advertisement

Quick Links

Commercial and Industrial Microgrid Energy
Storage Solution
Quick Guide (With SmartLogger-
based Microgrid Control)
Issue
01
Date
2023-12-18
HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the LUNA2000-200KWH-100KW-2H1 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Huawei LUNA2000-200KWH-100KW-2H1

  • Page 1 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With SmartLogger- based Microgrid Control) Issue Date 2023-12-18 HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei Digital Power Technologies Co., Ltd. and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a hazard with a medium level of risk which, if not avoided, could result in death or serious injury. Indicates a hazard with a low level of risk which, if not avoided, could result in minor or moderate injury. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 4 Changes between document issues are cumulative. The latest document issue contains all the changes in earlier issues. Issue 01 (2023-12-18) This issue is used for first office application (FOA). Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 5: Table Of Contents

    A Reference Documents......................51 B ESS Software Upgrade Solution for the Off-Grid PV+ESS System......54 C List of Alarms Affecting Topology Identification............56 D Digital Power Customer Service..................59 E Contact Information......................60 Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 6 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With SmartLogger-based Microgrid Control) Contents F Acronyms and Abbreviations....................62 Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 7: Solution Introduction

    5 kvar or above (5% of the PCS rated power), 5% even harmonics are allowed. When the PCS has no output fundamental wave current, loads with even harmonics cannot be connected. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 8: On/Off-Grid Pv+Ess System

    Table 1-1 Components of the on/off-grid PV+ESS system Name Model/Specifications Quantity Remarks Smart String ● LUNA2000-200KWH-2H1 ≤ 20 Purchased from Energy the Company ● LUNA2000-161KWH-2H1 Storage ● LUNA2000-129KWH-2H1 System (ESS) ● LUNA2000-97KWH-1H1 Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 9 Depending Purchased from Optimizer on the actual the Company ● SUN2000-600W-P (SUN2000P) quantity of (optional). ● MERC-1300W-P PV modules The SUN2000P is ● MERC-1100W-P supported only by the SUN2000-50KTL- Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 10 Meter at the DTSU666-HW or YDS60-80 Purchased from grid the Company connection point FusionSolar iMaster NetEco Purchased from Smart PV V600R023C00CP2101 and the Company Management later versions (optional) System (SmartPVMS) Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 11 Prepared by the with the coupler DOLD customer. Do not RP5898/61 connect the measurement cable of the IMD to circuit breakers or switches to prevent the measurement loop from being disconnected. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 12: Off-Grid Pv+Ess System

    ● LUNA2000-161KWH-2H1 Storage ● LUNA2000-129KWH-2H1 System (ESS) ● LUNA2000-97KWH-1H1 Smart Power LUNA2000-100KTL-M1 ≤ 20 Purchased from Control the Company. System The quantity (PCS) ratio of PCS to ESS is 1:1. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 13 ● SmartACU2000D-D-00 The SACU Controller ● SmartACU2000D-D-06 contains the (SACU) SmartLogger, which can be used to manage devices in an array over the web user interface (WebUI) of the SmartLogger. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 14 50 Hz/60 the customer ● iSitePower-M-(MAP05A1, Prepared by MAB05B1) or devices with the customer the same functions ● Power: ≥ 5 kVA ● Power backup duration ≥ 1 hour Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 15: Communication Logic

    (quantity of 10M/100M auto-sensing Ethernet ports ≥ 8). The quantities of switches and Ethernet ports are configured based on the quantities of ESSs and PCSs connected to the array. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 16 ESSs and PCSs connected to the array. In the PCS FE ring topology, a single FE ring network supports a maximum of 15 PCSs. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 17 FE, and ESSs communicate with each other through SFP optical fiber cascading. In the ESS fiber ring topology, a single fiber ring network supports a maximum of 15 ESSs. Figure 1-5 SACU+ESS fiber ring+PCS FE ring topology Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 18: O&M Methods

    SmartLogger A PC is connected to the Deployment commissioning SmartLogge WebUI SmartLogger in the SACU to r3000 User manage the ESSs, PCSs, Manual SUN2000s, and meters in the array. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 19 App User and the SUN2000 to locally device locally Manual manage a single PCS, ESS, and ● Upgrading the software SUN2000. version of a single device locally Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 20: Installation And Cable Connection

    N·m. Use a marker to mark the nuts after the torque is verified. Installing the Install the PCS on the side of the ESS using the delivered mounting brackets (including M12 bolt assemblies). Installing the SUN2000 and SUN2000P Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 21 Ensure that the phase sequence of the AC power cables of the PCS is consistent with that of the isolation transformer and power grid. Otherwise, the system may fail to run properly. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 22 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With SmartLogger-based Microgrid Control) 2 Installation and Cable Connection Step Task Precaution Installing For details about the cable connections, see communicatio Communication Logic. ns cables Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 23: Check And Preparation Before Power-On

    In an outdoor scenario, you are advised to power on the PSU within 24 hours after unpacking. If the PSU cannot be powered on in time, place it in a dry indoor environment without corrosive gas. Figure 3-1 Installing the PSU Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 24 Check whether the reading of the pressure gauge on the rack mounted fire extinguishing system is normal. Remove the communications cables between the rack mounted fire extinguishing system and the CMU. The SACU or SmartLogger WebUI shall report related alarms. ----End Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 25: System Power-On And Commissioning

    4.1 Device Power-On 4.1.1 On/Off-Grid PV+ESS System Power on the on/off-grid PV+ESS system when an external power supply is available. Figure 4-1 Power-on process of the on/off-grid PV+ESS system Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 26 (if any) between the SmartLogger3000A and the UPS based on site requirements. Powering on the Turn on the IMD power switch on the UPS side. UPS-IMD auxiliary power supply Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 27 Powering on the For details, see the documents provided by the isolation vendor. transformer Powering on the Turn on the AC switch between the PCS and the isolation transformer. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 28: Off-Grid Pv+Ess System

    Power on the off-grid PV+ESS system when the UPS can supply power, the DG is not running, and the power distribution equipment has no power supply. Figure 4-2 Power-on process of the off-grid PV+ESS system Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 29 2FCB2, TCUE power switch 2FCB3, fan 1 switch 2FCB6, fan 2 switch 2FCB7, air conditioner 1 switch 2FCB8, and air conditioner 2 switch 2FCB9 in sequence. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 30: Deployment Commissioning

    WebUI login, see the SmartLogger3000 User Manual. 4.2.2 Preparations Before Deployment Step 1 Click Maintenance, choose Device Mgmt. > Connect Device, and check that the devices are connected. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 31 Maintenance > Device Mgmt. > Connect Device and click Auto. Search. – If an ESM indicator is red, clear the ESM alarm according to the alarm handling suggestions. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 32 SmartLogger, PCS, ESS, and SUN2000 in FusionSolar Software Download. Choose Maintenance > Software Upgrade to check the software versions of the SmartLogger, PCS, ESS, and SUN2000. If the software version of each Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 33: Commissioning Using The Deployment Wizard

    Device disconnection time (choose Maintenance > Device Mgmt. > Connect Device to view Device disconnection time), and then click Search for Device to check cable connections and allocate addresses. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 34 ● After a device is added or deleted, you need to click Search for Device again in Deployment Wizard. Otherwise, the system topology will not be updated. Step 3 After the device search is complete, set the grid connection state based on site requirements. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 35 Apparent Power Baseline (kVA) You are advised to retain the default under Parameter Configuration value. Maximum Overload Active Power You are advised to retain the default (kW) under Parameter Configuration value. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 36 SmartLogger3000 User Manual . Figure 4-8 Connecting to power meters Step 5 (Optional) Connect to environment monitoring instruments (EMIs). Figure 4-9 Connecting to EMIs Step 6 Set battery control parameters. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 37 Confirm and set Detection start time to the optimal time. Step 7 Connect to a Huawei network management system (NMS). Set related parameters by referring to "Setting Parameters for Connecting to the Management System"...
  • Page 38 Figure 4-12 Connecting to third-party devices Step 10 Set microgrid parameters. Select No in the Do you want to connect the relay protection device? dialog box. Setting microgrid parameters Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 39 If Microgrid scenario is set to On-grid/Off-grid (PQ/VSG), refer to the following parameter description. Parameter Description Switch status Set these parameters based on the actual cable port under On/ connections. Off-grid switch Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 40 This DI port status function can be restored only after the SmartLogger under Load is restarted or the black start is successful in the off- Switch grid scenario. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 41: Checking The Phase Sequence

    Step 2 If the PCS reports a Reverse Phase Sequence on AC Side alarm: Shut down the PCS, and turn off the power switches on the AC and DC sides of the PCS. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 42 Turn on the power switches on the AC and DC sides of the PCS. Restart the PCS. Check and ensure that no Reverse Phase Sequence on AC Side alarm is reported. ----End Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 43: Microgrid Settings

    Set the DO port for turning on the on/off-grid switch port under On/Off- based on the actual cable connections. grid switch DI port under Grid Set these parameters based on the site requirements. Failure Detection Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 44 Set the maximum SOC for charge in off-grid charge SOC mode. The default value 90% is recommended. (off-grid) Min. SOC for Set the minimum SOC for black start. The black start default value 7% is recommended. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 45 Disable: The automatic microgrid adaptability control function is disabled. The microgrid adaptability of the inverter is not automatically set during on/off-grid switching. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 46 Monitoring > Inverter > Running Param. > Feature Parameters. 5. The SmartLogger sends a command to start the SUN2000. 6. The SmartLogger sends PV and ESS power scheduling commands. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 47 Monitoring > Inverter > Running Param. > Feature Parameters. 7. The SmartLogger sends a command to start the SUN2000. 8. The SmartLogger sends PV and ESS power scheduling commands. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 48: Off-Grid

    Table 5-7 General configuration parameters Parameter Description Grid Voltage under Set the rated voltage of the power grid. Microgrid Grid Frequency under Set the rated frequency of the power grid. Microgrid Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 49 This function can be restored only after the SmartLogger is restarted or the black start is successful in the off-grid scenario. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 50 Charging cutoff SOC > End-of-charge SOC (off-grid) ≥ SOC threshold for stopping load shedding > SOC threshold for starting load shedding > End-of-discharge SOC (off-grid) > Min. SOC for black start > Discharge cutoff SOC Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 51 6. If the SOC is less than the Min. SOC for black start, the PV+ESS system shuts down and remote black start cannot be performed. In this case, technical engineers are required to handle the problem onsite. ----End Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 52: System Operations

    Step 2 Send a startup command to the SUN2000, PCS, and Smart Rack Controller. Method 1 (array-level): Choose Maintenance > Connect Device, and click Method 2 (bus-level): Choose Overview > Plant Running Info., and click Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 53 Control > Black Start, ensure that Current Battery SOC is higher than Min. Battery SOC for Black Start. Otherwise, black start may fail. This operation will change the setting of On/Off-grid switching mode to No control. Confirm before you continue. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 54 Microgrid scenario is set to Off-grid, if the solar irradiance recovers for inverters and no PCS is running, turn off the load switch and then the black start is automatically triggered. ● Black start succeeded. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 55: System Power-Off

    Step 2 Power off the devices: Turn off the main power switches and then the auxiliary power switches of the devices by referring to the operations of 4.1 Device Power- in the reverse order. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 56 Quick Guide (With SmartLogger-based Microgrid Control) 7 System Power-Off NO TE To prevent local operations on switches during subsequent power-on, you are advised not to turn off the auxiliary power switches. ----End Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 57: A Reference Documents

    161KWH-2H1, 200KWH-2H1) Smart String ESS Maintenance Manual ● LUNA2000-(97KWH-1H1, 129KWH-2H1, 161KWH-2H1, 200KWH-2H1) Smart String ESS Quick Guide ● LUNA2000-100KTL-M1 Smart Power Control System User Manual ● LUNA2000-100KTL-M1 Smart Power Control System Quick Guide Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 58 SmartACU2000D Smart Array Controller Quick Guide (Dual Opto-Electronic Ethernet Switches) SmartLogger ● SmartLogger3000 User Manual ● SmartLogger3000 Quick Guide DTSU666-HW DTSU666-HW Smart Power Sensor Quick Guide FusionSolar app FusionSolar App User Manual Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 59 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With SmartLogger-based Microgrid Control) A Reference Documents Device Document iMaster NetEco iMaster NetEco V600R023C00 FusionSolar SmartPVMS User Manual Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 60: B Ess Software Upgrade Solution For The Off-Grid Pv+Ess System

    Step 6 Upgrade the software on the SmartLogger WebUI: Click Choose File, select the target software package, and click Upload. After the upload is complete, click Software Upgrade. Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 61 Battery SOC for Black Start. Otherwise, black start may fail. This operation will change the setting of On/Off-grid switching mode to No control. Confirm before you continue. Step 10 Turn on the load switch. ----End Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 62: C List Of Alarms Affecting Topology Identification

    Bus Side Overvoltage on Rack Controller 3020 Bus Side Reverse Polarity on Rack Controller 3021 Insulation Resistance of Rack Controller Abnormal 3022 Rack Controller Temperature High 3023 Battery Terminal Overtemperature on Rack Controller Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 63 Abnormal 3044 Battery Pack Overcurrent 3045 Battery Pack Temperature High 3046 Battery Pack Temperature Low 3047 Battery Pack Undervoltage 3052 External DC Auxiliary Power Supply of Rack Controller Fault Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 64 3849 Air Exhaust Malfunction 1, 2 3850 Combustible Gas Detection Malfunction 3856 Battery Fault Protection 1, 2 3858 48 V DC Auxiliary Power Supply Faulty 3859 Forced Dehumidification Started Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 65: D Digital Power Customer Service

    Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With SmartLogger-based Microgrid Control) D Digital Power Customer Service Digital Power Customer Service https://digitalpower.huawei.com/robotchat/ Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 66: E Contact Information

    To ensure faster and better services, we kindly request your assistance in providing the following information: ● Model ● Serial number (SN) ● Software version ● Alarm ID or name ● Brief description of the fault symptom Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 67 Quick Guide (With SmartLogger-based Microgrid Control) E Contact Information NO TE EU Representative Information: Huawei Technologies Hungary Kft. Add.: HU-1133 Budapest, Váci út 116-118., 1. Building, 6. floor. Email: hungary.reception@huawei.com Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 68 F Acronyms and Abbreviations Acronyms and Abbreviations Central Monitoring Unit Energy Storage System Fast Ethernet Power Control System Power Supply Unit SACU Smart Array Controller Small Form-factor Pluggable State of Charge Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 69 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With SmartLogger-based Microgrid Control) F Acronyms and Abbreviations State of Health Uninterruptible Power Supply Issue 01 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.