LUNA2000-200KWH-2H1 Smart String ESS
User Manual
Check
Item

9.1.4 SACU Installation Check

For details, see the
No PID
No.
1
2
3
4
5
6
7
8

9.2 Installing a PSU

Prerequisites
The PSU is secured inside the ESS during transportation and installed onsite.
Issue 03 (2023-03-30)
Expected Result
The AC maintenance compartment door is closed and the screws on
the door are tightened.
The DC maintenance compartment door is closed and the screws on
the door are tightened.
The waterproof plugs on the unused USB and COM ports are secured.
SmartACU2000D Smart Array Controller User Manual (with
Module).
Expected Result
The cabinet and all components are installed properly.
All upstream switches for the cabinet and all switches inside the
cabinet are OFF.
All cables are connected correctly and securely, without exposed
metal.
Cables are bound neatly, and cable ties are secured evenly and
properly in the same direction.
Routing for the power cables and signal cables meets the
requirements for routing electrical and ELV cables and complies with
the cable routing plan.
The locking caps of the used waterproof connectors are tightened and
sealed. Unused waterproof connectors are plugged and the locking
caps are tightened.
The cabinet interior is clean, without dust, dirt, or foreign matter.
The paint on the cabinet exterior is intact. Immediately repaint the
part where paint flakes off to prevent corrosion.
Copyright © Huawei Digital Power Technologies Co., Ltd.
9 System Power-On
120

Advertisement

Table of Contents
loading

This manual is also suitable for:

Luna2000-200kwh-100kw-2h1

Table of Contents