Huawei LUNA2000-200KWH-2H1 User Manual page 80

Smart string ess
Hide thumbs Also See for LUNA2000-200KWH-2H1:
Table of Contents

Advertisement

LUNA2000-200KWH-2H1 Smart String ESS
User Manual
Stage
Before hoisting
During hoisting
Issue 03 (2023-03-30)
Precautions
Crane hoisting capacity > 1 t, working radius ≥ 2 m. If the
onsite environment does not meet the required working
conditions, ask a professional to assess the conditions.
Only trained and qualified personnel are allowed to perform
hoisting operations.
Check that hoisting tools are complete and in good
condition.
Ensure that the hoisting tools are secured to a load-bearing
object or wall.
The weather condition should be good without wind when
the equipment needs to be hoisted outdoors.
Ensure that the crane and steel ropes meet the
requirements before the hoisting.
All doors of the equipment are closed and locked.
Ensure that the steel hoisting ropes are securely connected.
It is recommended that the equipment be hoisted from left
to right or from right to left.
Do not allow any unauthorized person to enter the hoisting
areas and do not stand under the crane arm.
Ensure that the crane is properly located and avoid long-
distance hoisting.
Keep the cabinet stable and horizontal during hoisting, and
ensure that the diagonal gradient of the cabinet is less than
or equal to 5 degrees.
Ensure that the angle between two ropes is less than or
equal to 90 degrees.
Lift and land the cabinet slowly to prevent shock to
equipment inside it.
Remove the ropes after ensuring that the cabinet is placed
evenly on the cabinet base.
Do not drag steel ropes or lifting appliances. Do not collide
with the equipment.
Secure the cabinet you have hoisted before hoisting another
cabinet.
Copyright © Huawei Digital Power Technologies Co., Ltd.