Loading/conveying material
- Use switch (1) to open the hopper.
Instruct the truck driver to dump the material.
- Set the switches for the auger (2) and the conveyor (3) to "auto".
- Set the switches for the auger and the conveyor on the remote controls (if applica-
ble) to "auto".
- Switch the conveyors on.
The conveyor limit switches (A) must switch off when the material has approximate-
ly reached the area beneath the auger crossbeam.
- Check that the material is transferred properly.
Manually switch on or off the conveyor if the material is not conveyed properly until
a sufficient amount of material lies in front of the screed.
D 42 21