14.1) Check of wiring

General note
The following steps have to be carried out:
Procedure
Step
1
2
3
4
5
6
7
8
Effectivity: 912 Series
Edition 2 / Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
Risk of electric shock!
WARNUNG
WARNING
Switch off ignition and remove key!
Risk of Burns!
WARNUNG
WARNING
Hot engine parts!
Always allow engine to cool down to ambient tempera-
ture before start of any work.
Inspect all cable connectors and their connections for tight fit, good contact,
corrosion or damage and replace as necessary.
Inspect all ground connections for corrosion and damage, replace if necessary.
Inspect plug connections between pick-up cable, electronic module, charging
and shorting cables for corrosion or damage and replace as required.
Inspect plug connections between electronic module and ignition coils for cor-
rosion or damage and replace if necessary.
Verify plug connections of alternator cables with rectifier-regulator and connec-
tions of all cables on rectifier-regulator for good contact, tight fit, corrosion or
damage and replace if necessary.
Inspect grounding cables for tight fit, corrosion or damage and replace if nec-
essary.
Verify shielding of cable assemblies for corrosion or damage, good ground con-
tact and tight fit, inspect the attachment of the shielding and replace if neces-
sary.
Inspect all 8 ignition cables to spark plug connector for corrosion or damage
and tight fit and replace if necessary.