Status displays of the production orders

Status
Created
The order has been created or has been taken over from the
PPS system. No batches have as yet been assigned to the
order.
Planned
Batches have been assigned to the order but have not yet
been started.
Executing
At least one batch in the order is being processed (in other
words, is running, paused, in error, or even has aborted).
Finished
All of the batches in the order have finished successfully.
Completed
All corresponding batches in the order have completed.
Exported
All batches and the order itself have been exported.
Meaning